Planning lines not considering order modifiers when created via accept order promising

$
0
0
Can anyone please help me figure out why planning lines that are created by accepting order promising are not considering order modifiers?

Example;
Component item - Lot-for-Lot - Critical - Minimum Order Qty=12 - Order Multiple=12
Produced Item - Lot-for-Lot - No order modifiers

If I create a sales order for quantity 20 - then calculate order promising and accept it - the planning lines are as follows;
Produced Item = Quantity 20
Component Item = Quantity 20 - this is incorrect because it is not considering the order modifiers

If I delete those planning lines and then calculate a regenerative plan - the planning lines are as follows;
Produced Item = Quantity 20
Component Item = Quantity 24 - this is correct because it is considering the order modifiers

Any feedback is much appreciated.