Item Charges and Subcontract PO Lines NAV2016

$
0
0
We have an issue where NAV won't let us assign Item Charges to Subcontract PO Lines. It gives an error if the PO Line/receipt has a Work Center assigned to it, which of course Subcontract PO's do. I understand that this is not a PO line for an Item, but there is freight paid in the process that we want in the multiline Production Order/Purchase Order, and Item Charges would be helpful. Has anyone found a workaround for this, besides painfully computing this and add then consuming it on the Prod Order?
Thanks,